Avoiding the default extension: re-procuring term maintenance

Many term maintenance contracts are extended not because extension is the best option, but because there was no time to do anything else. Starting early changes that.

How default extensions happen

Contract expiry is years away, and then it isn't. Strategy, market engagement, specification, evaluation, award and mobilisation all take time, and for a major highways contract the timeline is longer than most people expect.

By the time the work starts in earnest, extending the incumbent can look like the only safe route.

Work back from the start date

Begin with the date the new contract must be running. Then allow time for mobilisation, standstill, evaluation, the tender period, market engagement and internal approvals.

For a large term contract, that usually means starting well over a year before expiry, and often closer to two.

Use the time to test the model

An early start lets you ask whether the current scope still fits. What should be bundled and what should stand alone? Would a priced schedule of rates, a target cost or another pricing model suit the work better?

These are the questions that get skipped when time is short.

Talk to the market properly

Market engagement isn’t a formality. Good suppliers will tell you what makes a contract attractive to bid and deliver, and where risk is in the wrong place.

In Herefordshire, market engagement produced 11 recommendations that shaped the final procurement.

Design for performance, not just award

Set the KPI regime, incentives and governance as part of the procurement rather than after it. Plan mobilisation and exit from the start, so the contract is ready to run on Day 1 and ready to end well.

If extension is right, make it a decision

Sometimes extending is the right call. When it is, treat it as a decision rather than a default: renegotiate where you can, and fix the issues you’d otherwise carry into the next contract.